See below for answers to frequently asked questions (FAQs). We will update FAQs regularly as the project progresses.
Three construction precincts will be established along the alignment: the southern, central and northern precinct. Each precinct will accommodate tunnelling operations and surface level construction work to build the lowered motorway and associated urban infrastructure.
The precincts will be purpose built to suit the construction activities taking place in that area. Detailed precinct layouts will be made available as planning is finalised.
Generally, precincts will include:
a tunnel access ramp where the TBMs will enter and exit the tunnels. These ramps are permanent structures that will become the lowered motorway when the tunnelling works are completed. Construction of the ramps involve building large retaining walls and bulk excavation of ground material
an electrical power substation to support tunnel operations such as powering the TBMs and other ancillary equipment like conveyors, lights, fans and pumps
enclosed conveyors to shift the excavated spoil from the tunnels to the spoil shed
an acoustic shed for management of spoil (the excavated rock and soil), storage of machinery and equipment, and to keep noise and dust to a minimum
a water treatment plant to ensure wastewater and run-off from the construction area meets required water quality before disposal
gantry cranes
worker facilities.
Construction hours differ between surface works and tunnelling.
Surface works will normally take place:
Monday to Saturday between 7:00 am and 7:00 pm
Sundays and Public Holidays from 9:00 am to 7:00 pm
While every attempt is made to complete construction work during the day, some night work will be required when traffic volumes are lower and safety can be maintained for motorists, pedestrians and our workers.
Other reasons for night work include:
third party approval limits work to night works
service outage timing determined by the relevant service provider
as agreed with adjacent stakeholders (there may be a preference to carry out the work at night) .
Tunnelling activities will take place 24 hours per day, seven days a week. This includes excavation by tunnel boring machines and tunnel support activities such as spoil handling and loading.
The tunnels will be constructed using tunnel boring machines (TBMs), except for short lengths at each end of the tunnels where the roadway is too shallow for the effective use of TBMs.
For these short lengths, the tunnels will be constructed from the surface by a process called cut and cover tunnelling. This construction method involves excavating a large open trench using an excavator (cut) and constructing the roof to give a tunnel-like finish (cover). Spaced concrete beams will form the roof giving an open tunnel finish.
A large part of the tunnelling operation involves the removal of ground material, referred to as spoil, from the newly excavated tunnel. Modelling and calculations have identified approximately 7.5 million tonnes of spoil will be generated during tunnelling and excavation for the open motorway construction.
Prior to construction starting, extensive ground investigation works have taken place to confirm the geotechnical and groundwater properties along the tunnel alignment. The ground is largely clay-based which is a soft ground material requiring specialist tunnelling methodology.
Once the clay is excavated, trucks move the spoil from the back of the TBM conveyor to a spoil shed on the surface within the site compound and then treated as required. From this shed, spoil is transported by truck with trailers (spoil haulage trucks) to various approved disposal sites across South Australia.
Several measures are implemented on site to ensure the safe management of spoil:
Prior to being removed from site, the spoil is tested and categorised so that it is directed to the correct disposal site.
Contaminated materials are handled in accordance with Construction Environmental Management Plan (CEMP) requirements.
Spoil haulage trucks are fitted with covers to minimise dirt tracking. The covers can be off when there is no spoil in the trailer.
Wheel wash systems installed at each site ensure that truck tyres are clean before leaving.
Options for the beneficial reuse of spoil will be explored where possible.
Construction of the open motorway between two sections of tunnels allows for connectivity to key east and west destinations such as Adelaide CBD, Adelaide Airport, Anzac Highway and other main connector roads.
The design uses a combination of tunnels, lowered and ground-level motorways, as well as overpasses and underpasses to provide the best access to these travel gateways. The design also preserves important cultural and heritage sites, opens up suburbs to new recreational spaces and minimises the extent of property acquisition as much as possible.
The tunnel boring machines used to excavate the tunnels will bore deep underground at around 10 to 25 metres below the surface. To view the planned location and depth of tunnels in proximity to your property, visit the Tunnel tool.
Safety has been at the forefront of the T2D Project design. The tunnels will have a range of features to make sure motorists are safe.
The T2D Project will be a ‘managed motorway’. This means the motorway and the tunnels will have a range of technology-based information, communications and control systems in the motorway, known as intelligent transport systems (ITS).
The systems are designed to actively:
manage traffic flows
improve safety
provide travel time reliability.
We will establish a dedicated traffic management centre to monitor the T2D motorway. It will have a range of tools to make sure traffic moves efficiently along the corridor. This includes measures such as:
coordinated ramp signalling
speed and lane use management
automated incident detection
variable messaging signs (VMS).
If an incident occurs in a tunnel, we will use these systems to coordinate an appropriate response to make sure motorists are safe.
Systems include:
tunnel closure system, so the tunnels can be safely closed when required using boom gates and stop signs to restrict access
automatic incident detection to identify hazards such as stopped vehicles, debris, animals or people
CCTV cameras for constant road monitoring and quick incident management
dynamic variable message signs to provide information to motorists like incident warnings and likely travel time
lane use management system to control speed limits and lane closures for optimised traffic flow and safety
fire detection and suppression systems to activate sprinklers in the event of a fire
radio rebroadcasting, so traffic management centre personnel can broadcast safety messages to motorists in the tunnels via their vehicle’s radio.
Tunnel boring machines (TBMs) are expected to produce some ground-borne noise as they excavate and line the tunnels. Due to the depth of tunnels and the ground conditions, noise from tunnelling is not expected to be heard in properties above the tunnels. As TBMs advance at approximately eight to ten metres per day, they’re typically expected to pass beneath a property in around three days.
There will be some noise from tunnelling activities audible at the tunnel portals during construction. Acoustic sheds will be built at each portal to minimise the amount of noise generated by tunnelling activities.
Weekly email updates will provide the latest TBM locations.
Vibrations from TBM operations are not expected to be felt at the surface and will be well below the thresholds that could cause structural damage. Long-term vibration monitors are installed along the construction site boundary to monitor vibration levels in real-time during construction works. Construction levels and mitigation measures are managed in accordance with relevant project approvals.
We will offer eligible properties in the vicinity of the tunnels and the surface level sites a free property condition survey both prior to work starting and once work is completed. Please see the information about property condition surveys.
This is standard process on major transport projects delivered by the Department for Infrastructure and Transport and will give people a clear understanding of the condition of their property before works occur and confirm the condition of the property after the TBMs have passed underneath and the tunnel is constructed.
We will do our best to minimise disturbance from our surface construction sites to nearby residents and businesses, however some construction activities will generate periods of noise.
We’ll use a range of measures to mitigate noise and vibration impacts, including:
providing advance notice of works to those nearby
monitoring noise and vibration levels during construction
applying at-source measures including temporary and permanent noise walls, noise blankets around mobile work areas and acoustic sheds to enclose tunnelling activities
planning activities to avoid project vehicles and trucks queuing and idling near homes and businesses
checking our equipment, vehicles and machinery are in good working order
limiting truck movements on local roads where possible
locating equipment as far as practical from homes and businesses
implementing respite and relocation measures
administering the Noise Treatment Program at eligible properties.
Due to the nature of the activities taking place, construction work can sometimes generate dust.
To minimise dust leaving the construction sites we will implement various mitigation measures including, but not limited to:
water carts on-site and on adjacent streets to dampen stockpiles, hardstand areas and road surfaces
street sweepers on haulage roads and local roads
polymer binding agent applied to stockpiles
spoil shed enclosing soil deposits
maximising the amount of hardstand area on-site.
Road tunnels can help reduce air pollution by moving vehicles underground and off the roads where people live and work. Road tunnels also reduce travel time and congestion by removing the number of traffic lights along the journey and reducing road grades (steepness) and corners.
Within the tunnel environment, vehicle emissions can be controlled and dispersed more effectively, resulting in little, if any, change in air quality for people living and working near the tunnel. Our tunnels are built to meet strict air quality standards using state-of-the-art ventilation and tunnel design.
The exit points of tunnels are also known as tunnel portals. During the design process, a modelling-based assessment is used to evaluate potential changes to the air quality surrounding these portals. It is necessary to demonstrate minimal or no change to the surrounding air quality.
During operation of the tunnels, emission levels are measured using air-quality monitors installed both inside and outside the tunnels to confirm that air quality standards are being met.
Residential, commercial, and industrial areas, as well as natural events like bush fires all contribute to air pollution. Motor vehicles also add to emissions, with other major contributors including wood heaters and industry.
By relocating surface traffic into tunnels, we can also use more space for things that matter most to Adelaide’s communities, including open green spaces and trees.
Further information about air quality management will be made available shortly once design is finalised. In the meantime, the T2D engagement team is happy to answer any questions you may have.
We are committed to maintaining two lanes of traffic in each direction on South Road during construction. There may be occasional limited closures at night or other off-peak times to facilitate some construction activities. The majority of construction will be undertaken off-site and next to South Road, which will limit impacts to existing traffic.
New Variable Message Signs (VMS) will be installed at key locations to advise motorists of traffic conditions along and around South Road with real-time information.
Use our Surface works map to see what’s happening in your local area and to help you plan ahead. It is updated weekly with the latest work activities.
You can also register for weekly email updates.
Some Adelaide Metro bus stops along South Road may be temporarily impacted while work is underway. Advance notice will always be provided ahead of any public transport changes.
Use our Surface works map to see what’s happening in your local area help you plan ahead. It’s updated weekly with the latest work activities including any public transport changes. Please observe bus stop signage and visit www.adelaidemetro.com.au for the latest information on routes and timetables.
Some changes to active transport routes may be required while work is underway. Detour routes will be signposted around our work sites for bike and shared-user paths.
Use our Surface works map to see what’s happening in your local area help you plan ahead. It is updated weekly with the latest work activities including any changes to active transport routes.
Access to properties will be maintained during construction unless otherwise agreed with the property owner or tenant. Where primary access is impacted by construction activities, alternative access will be arranged with the owner or tenant and advance notice will always be provided.
Wherever possible, residents, deliveries and service vehicles will be permitted access through local road closures.
If you have special access needs and/or mobility issues please contact us to discuss your needs and we'll work with you to provide alternative access.
Emergency services are regularly briefed throughout construction to ensure they’re kept up to date with the latest project information and access is always maintained. We consult with emergency services as part of the planning process ahead of any planned traffic changes.
The T2D Project will need a broad set of skilled workers across hundreds of different roles during construction. It will support 5,500 jobs per year on average during main construction, creating a skills legacy for South Australia.
The project is committed to providing opportunities for local people, Aboriginal workers, apprentices, trainees and job seekers who are long-term unemployed.
Jobs will include hands-on, supervisory and engineering roles in construction. Most jobs will involve working on-site but office-based corporate, drafting and project management roles will also be available.
If you would like to register your interest to work on the T2D project please see our Employment opportunities page.
A property condition survey is an inspection of a building or property to assess and document its general condition including any existing defects. The survey is offered before substantial construction on the surface or tunnelling begins in your area.
If a pre-construction property condition survey is completed for your property, you will automatically be offered a post-construction property condition survey. A post-construction property condition survey is a follow-up inspection after construction work is completed. It can be used to determine if there are any changes to the buildings or structures, offering owners peace of mind during construction work.
To learn more about property condition surveys and who is eligible for one please visit our property condition surveys page.
The best way to stay up to date on the project is to register for updates.
Visit our T2D Community Information Centre to learn more about the T2D Project and speak to our friendly team.
Where: 290 South Road, Hilton.
Holiday hours 2024:
Please be advised the center will be closed from 19 December 2024 to 6 January 2025 for the holiday season.
We will reopen by appointment only from 6 January to 11 January.
To make an appointment please use the contact details below.
Regular business hours will resume on 13 January 2025.
We appreciate your understanding and wish you a wonderful holiday season.
Opening hours:
10am to 3pm on Mondays, Tuesdays and Wednesdays
9am to 1pm on Saturdays (first Saturday of every month)
info@T2Dalliance.com.au
1300 951 145